Type
Internal restructuring
Country
Hungary
Region
Dunantul; Kozep-Dunantul; Komarom-Esztergom
Location of affected unit(s)
Oroszlány
Sector
Utilities
Electricity, Gas, Steam And Air Conditioning Supply
Electricity, Gas, Steam And Air Conditioning Supply
35 - Electricity, gas, steam and air conditioning supply

310 jobs
Number of planned job losses
Job loss
Announcement Date
11 June 2009
Employment effect (start)
1 July 2009
Foreseen end date
31 December 2009

Description

Vértesi Erőmű Zrt, a Hungarian power plant, is to dismiss 310 workers from its 1,860 strong workforce.

The scale of the measure is smaller than had been expected as the company's original plans for this year included the dismissal of another 170 employees, while its owner, the Hungarian Electricity Company (Magyar Elektromos Művek, MVM), a state owned enterprise, considered its immediate closure.

The final decision was made after a governmental decree prescribed that MVM was to continue operations while implementing a strict austerity plan that included, among other measures, the implementation of an efficiency enhancement program, and the selling of properties.

Vértesi Erőmű Zrt. is made up of a carbon based power plant that produces 240 MW of electrical and 84 MW of heat power; and a supplying carbon mine in Márkushegy.

 

 